一篇很通俗的介绍合同类型的文章

What are different Types of Contract?

Types of Contract – Example and Explanation

Procurement Management is considered as a difficult topic for the PMP® Exam. However, in my opinion, Procurement Management is one of the easier topics for the PMP® Exam.

So, Why do PMP® Aspirants find Procurement Management difficult?

I believe this is due to lack of experience in Procurement Management. Usually, PMP® Aspirants are well-experienced and knowledgeable about other aspects of Project Management. But, over the time, I have noticed that most of the PMP® Aspirants do not have relevant Procurement Management experience. They have not done procurement in their official capacity. I think practical experience is always useful for understating a PMP® Exam topic.

Let us make Procurement Management Easy for the PMP® Exam.

You may not have done any Procurement in your office. But as adults you would have definitely done Procurement at home. You would have certainly bought a vehicle or made arrangements for a family vacation. I believe understanding Procurement Management (in fact any Project Management topic) can become easy if you correlate the PMBOK® Guide concepts with your daily life.

We will discuss Types of Contract in this article and leave other aspects of Procurement Management for another day. Let us understand Types of Contract by looking at one such small example. There are 3 basic Types of Contract:

Fixed Price (FP) Contracts

Cost Reimbursable (CR) Contracts – This is also called Cost Plus (CP) Contracts

Time and Material (T&M) Contracts

Let us understand these 3 basic Types of Contract. There are some sub-categories of basic Types of Contract also. We will not discuss the sub-categories in this article. Let us understand basic Types of Contract with the help of a small example.

Note: You can refer to Max Wideman Glossary to read some standard definitions on Types of Contract.

Example – House Renovation Project

Let us assume that we have to do a house renovation project. As part of renovation we need to rewire the whole house. There would be 2 broad Cost Components for the rewiring the house

Human Resource (HR) Cost e.g. Labor Cost

Material Cost e.g. Wire Cost

Let us also assume that we (Buyer) have called an Electrical Contractor (Seller) to lay the electricity wire. We asked the Contractor to provide us with a Quotation for re-wiring the house.

So, how would the Contractor prepare a Quotation?

The Contractor would start with an estimate of costs. The Contractor would consider aforementioned costs components (HR Costs & Material Cost) to arrive at an Estimate. There could be three different scenarios for arriving at an Estimate. The Contractor can potentially choose one of the possible three scenarios to arrive at an Estimate. The three scenarios would depend on

how much information we (as a buyer) have shared with the Electrical Contractor

what are the market (economic) conditions.

Let us take a look at these 3 scenarios in detail.

Scenario I – Fixed Price Quotation

Let us assume we called a Building Architect before calling the Electrical Contractor. The Architect provided us with complete Electrical Layout & Design. The Architect also gave us Material Specifications of the Wiring to be used. In brief we finalized everything before the Contractor walked in. We prepared a detailed Statement of Work for the Contractor. The contractor would study the detailed Statement of Work (finalized designs and material specifications) to provide a Fixed Cost Estimate.

HR Cost – The contractor would look at the whole house and architectural design to estimate how many Labor units (duration & effort) would be required to complete the work.

Material Cost – The contractor would survey the house and study the Electrical Layout & Design to make an approximation of how much Wire (quantity of wire) would be required.

Based on above two estimates, the Contractor can estimate Cost of Labor and Cost of Wire. The Contractor would total these Estimates and add some profit to provide us with a Fixed Price Quotation. This Quotation (once finalized and accepted by us) would become part of the Contract. We will have to pay a Fixed Price to the Contractor for completing the work. Even if the Contractor overruns his estimates, we would not be liable to pay anything extra.

Salient Features of FP Contracts

In FP Contracts Scope is well defined and Price is Fixed.

FP Contracts could run into losses for the Seller if the costs are not managed well. FP Contracts are more risky for Sellers.

Scenario II – Time & Material Quotation

This scenario would come if Electrical layout & design was not available with us. We will not be able to provide a detailed Statement of Work to the Contractor. The Contractor would have to prepare the Quotation without a detailed Statement of Work.

HR Cost – Since the Electrical Layout & Design are not available, the Contractor would not be able to estimate how much Labor units (duration & effort) would be required to complete the work. The Contractor can, however, estimate the Labor Rate per Day (or any other unit of time e.g. hour or week).

Material Cost – Again the Contractor would not be able to estimate the quantity of wire that would be required to complete the work. The Contractor can, however, estimate the Rate per Meter (or any other unit of quantity e.g. Kg) for different types of wires required.

The contractor would add a suitable margin to estimated Labor Rate & Wire Rate for re-wiring the house. The Contractor would provide top-up Rates to us as a Rate Quotation. These Rates (once finalized and accepted by us) would become part the Contract. These Rates will remain Fixed for the duration of the Contract. We will have to pay the Fixed Rateto the Contractor for completing the work. The actual quantity of Labor and Material consumed will be used for making final payments.

Salient Features of T&M Contracts

In T&M Contracts Quantity is not defined and Rate is Fixed.

In T&M Contracts both Buyer and Seller can overrun their estimated Cost targets. T&M Contracts are risky for both Buyers and Sellers.

Scenario III – Cost Reimbursable or Cost Plus Quotation

This scenario is similar to Scenario II above. This scenario would come if Electrical layout & design was not available with us. We will not be able to provide a detailed Statement of Work to the Contractor. The Contractor would have to prepare the Quotation without a detailed Statement of Work.

In addition, let us assume that Market (Economic) Conditions are constantly changing. There is a constant fluctuation of Labor Rates and Wire Rates in the market. In these conditions, the Contractor cannot reasonably estimate a Fixed Rates.

In this Scenario, the Contractor would propose (since Labor Rate & wire Rate cannot be fairly estimated) that the Actual Costs incurred by her/him should be Reimbursed. In addition, the Contractor, would ask for a Suitable Fee for the services that she/he would render to complete the work. This proposal (once finalized and accepted by us) would become part the Contract. Neither the Rates nor the Quantity would be Fixed for the duration of the Contract. A Service Level Agreement, however, can be defined as part of the Contract. We will have to Reimburse all legitimate Costs and give a Suitable (Agreed upon) Fee to the Contractor.

Salient Features of CP Contracts

In CP Contracts neither the Rate nor the Quantity is defined.

CP Contracts could be a huge overhead for the Buyer if costs are not managed well. CP Contracts are more risky for Buyers.

Conclusion

Who has more Risk in different Types of Contract?

Fixed Price – Seller has more Risk

Time and Material – Buyer and Seller share Risk

Cost Plus – Buyer has more Risk

You should read my other article on that provides a formal explanation of different Types of Contract. It will help you in the PMP® Exam preparation.

Please leave a comment if you have any specific question.

Related Articles

difference between a Project Charter and Contract

Image courtesy of Jeroen van Oostrom at FreeDigitalPhotos.net

#CONTRACT TYPE#DEFINITIONS#PROCUREMENT MANAGEMENT


Praveen Malik, PMP

​Praveen Malik ​is a certified Project Management Professional (PMP®) with a rich 23+ years of experience. He is a leading Project Management Instructor, Coach and ​Advisor. He ​has successfully trained thousands of aspirants for the PM certification exams.

最后编辑于
©著作权归作者所有,转载或内容合作请联系作者
  • 序言:七十年代末,一起剥皮案震惊了整个滨河市,随后出现的几起案子,更是在滨河造成了极大的恐慌,老刑警刘岩,带你破解...
    沈念sama阅读 221,273评论 6 515
  • 序言:滨河连续发生了三起死亡事件,死亡现场离奇诡异,居然都是意外死亡,警方通过查阅死者的电脑和手机,发现死者居然都...
    沈念sama阅读 94,349评论 3 398
  • 文/潘晓璐 我一进店门,熙熙楼的掌柜王于贵愁眉苦脸地迎上来,“玉大人,你说我怎么就摊上这事。” “怎么了?”我有些...
    开封第一讲书人阅读 167,709评论 0 360
  • 文/不坏的土叔 我叫张陵,是天一观的道长。 经常有香客问我,道长,这世上最难降的妖魔是什么? 我笑而不...
    开封第一讲书人阅读 59,520评论 1 296
  • 正文 为了忘掉前任,我火速办了婚礼,结果婚礼上,老公的妹妹穿的比我还像新娘。我一直安慰自己,他们只是感情好,可当我...
    茶点故事阅读 68,515评论 6 397
  • 文/花漫 我一把揭开白布。 她就那样静静地躺着,像睡着了一般。 火红的嫁衣衬着肌肤如雪。 梳的纹丝不乱的头发上,一...
    开封第一讲书人阅读 52,158评论 1 308
  • 那天,我揣着相机与录音,去河边找鬼。 笑死,一个胖子当着我的面吹牛,可吹牛的内容都是我干的。 我是一名探鬼主播,决...
    沈念sama阅读 40,755评论 3 421
  • 文/苍兰香墨 我猛地睁开眼,长吁一口气:“原来是场噩梦啊……” “哼!你这毒妇竟也来了?” 一声冷哼从身侧响起,我...
    开封第一讲书人阅读 39,660评论 0 276
  • 序言:老挝万荣一对情侣失踪,失踪者是张志新(化名)和其女友刘颖,没想到半个月后,有当地人在树林里发现了一具尸体,经...
    沈念sama阅读 46,203评论 1 319
  • 正文 独居荒郊野岭守林人离奇死亡,尸身上长有42处带血的脓包…… 初始之章·张勋 以下内容为张勋视角 年9月15日...
    茶点故事阅读 38,287评论 3 340
  • 正文 我和宋清朗相恋三年,在试婚纱的时候发现自己被绿了。 大学时的朋友给我发了我未婚夫和他白月光在一起吃饭的照片。...
    茶点故事阅读 40,427评论 1 352
  • 序言:一个原本活蹦乱跳的男人离奇死亡,死状恐怖,灵堂内的尸体忽然破棺而出,到底是诈尸还是另有隐情,我是刑警宁泽,带...
    沈念sama阅读 36,122评论 5 349
  • 正文 年R本政府宣布,位于F岛的核电站,受9级特大地震影响,放射性物质发生泄漏。R本人自食恶果不足惜,却给世界环境...
    茶点故事阅读 41,801评论 3 333
  • 文/蒙蒙 一、第九天 我趴在偏房一处隐蔽的房顶上张望。 院中可真热闹,春花似锦、人声如沸。这庄子的主人今日做“春日...
    开封第一讲书人阅读 32,272评论 0 23
  • 文/苍兰香墨 我抬头看了看天上的太阳。三九已至,却和暖如春,着一层夹袄步出监牢的瞬间,已是汗流浃背。 一阵脚步声响...
    开封第一讲书人阅读 33,393评论 1 272
  • 我被黑心中介骗来泰国打工, 没想到刚下飞机就差点儿被人妖公主榨干…… 1. 我叫王不留,地道东北人。 一个月前我还...
    沈念sama阅读 48,808评论 3 376
  • 正文 我出身青楼,却偏偏与公主长得像,于是被迫代替她去往敌国和亲。 传闻我的和亲对象是个残疾皇子,可洞房花烛夜当晚...
    茶点故事阅读 45,440评论 2 359

推荐阅读更多精彩内容