2022-03-13(180)Engineering law and the ICE Contracts

CHAPTER 1

Background to the Contract Forms:

General Law of Contract

The forms of tender, agreement, conditions and bond published by the Institution of Civil Engineers, etc., and the Association of Consulting Engineers’ Service Agreements are designed to standardise the duties of contractors, employers and engineers and to distribute fairly the risks inherent in civil engineering.

The contract system on which these forms are based has been in use for over a century, and the present practice is outlined in a report published by the Institution, so that it is not necessary to say anything about it here. 

The forms themselves—in general use since about 1950—have defects, but are not as defective as many of the forms concocted by individual engineers and contractors used before then. They have the great advantage that their contents become known and understood with constant use, so that they have reduced the number of disputes and misunderstandings. 

From a practical point of view the use of the forms is now so widespread that they are really a private code of legislation which is automatically accepted by individual employers and contractors, subject to adjustments for special cases, rather than an agreement on terms which are bargained for in detail between them. Nevertheless, it is normally the ordinary law of contract which applies—the branch of the law which regulates rights and duties not imposed by the law but created by the parties’ own agreement with each other. To be dealt with first, therefore, are four general topics relating to the law of contract. 

Essentials of a valid contract. The basic requirements of the courts before they will enforce a private agreement as a legal contract are, very briefly because they will not often be in question in relation to construction or service contracts—

(a) CERTAINTY. Since it is the agreement of the parties which gives binding force to a contract, the terms of their agreement must be sufficiently certain to have a practical meaning. To create a contract the parties must not have failed to agree on any term which 

“even though the parties did not realise it, was in fact essential to be agreed, as a term of the contract, if the contract was to be commercially workable”. The courts will help—if, for example, no price is fixed they may imply that a reasonable price is to be paid—but they cannot make the contract for the parties: 

Defendant sued on an agreement to buy a van. A deposit had been made but all that was said about the balance of the price was that it was to be paid “on hire-purchase terms”.

Held: “hire-purchase terms” vary so much that it was impossible to say what the parties intended to agree to, and there was no binding contract. 

Contractors submitted two tenders for construction of a freight terminal. One tender was at a fixed price, and the other had a price variation clause. There was a steep rise in costs after tender, and the contractors wrote to the employers asking for sympathetic consideration of revision of the prices quoted for the fixed price tender. The employers wrote to the contractors that they accepted “your tender”. No contract was signed, and it was held that as the employers had not made it clear which tender they were accepting, there was no concluded contract and the contractors were entitled to payment on a quantum meruit (see below) for the works, which they had completed. 

Agreement that a developer’s quantity surveyor would negotiate with a builder—“fair and reasonable contract sums in respect of each of the three projects as they arise. (These would incidentally be based upon agreed estimates of the net cost of work and the general overheads with a margin for profit of five per cent)…”. Negotiations on prices eventually broke down. Held that there was no concluded contract. There was no agreement on the price or any method by which the price was to be calculated, not dependent on agreement being reached by the parties in further negotiations. An agreement to negotiate a fundamental term of a contract such as price is too uncertain to be enforced by the courts. 

It is not often nowadays that the main contract is not tied up, because the procedure has become stereotyped. Lack of similar procedure in engineers’ offices (in the case of nominated sub-contractors) and on the part of contractors and sub-contractors for making sure that all sub-contracts are in order, is one of the reasons why a high proportion of the legal troubles in construction work now are about sub-contracting.

A common sequence is a quotation from a sub-contractor containing on the back, in small print, conditions of contract trying hard (but not always successfully in law) to shed legal responsibility. The main contractor replies with an “acceptance” of tender, which says that all conditions put forward by the sub-contractor are to be null and void and contain its own conditions, placing the sub-contractor at the mercy of the main contractor. There may also be discrepancies between the quotation and acceptance about attendances and coordination of programmes. These differences are either ignored or, while efforts are being made to sort them out, the work starts. As a result it may be extremely difficult to decide what are the terms of the contract between the parties, or because of the lack of agreement on all the points raised there may be no contract at all and either party may lose unfairly. The sub-contractor may have no remedy for breach of contract if he is put off the site. Because even an agreed price does not bind unless the contract as a whole is agreed, the sub-contractor may be entitled to payment on a quantum meruit for the work done (i.e. literally “as much as he has earned”, that is reasonable payment, which may be based on cost plus profit). 

For letters of intent refer to p. 18, and for incorporation of standard terms p. 26.

A word of warning is necessary: legislation intended to prevent abuse of the freedom to contract may now alter the effect of the agreed terms of a contract. Chapter 16 deals with the most important cases.

©著作权归作者所有,转载或内容合作请联系作者
  • 序言:七十年代末,一起剥皮案震惊了整个滨河市,随后出现的几起案子,更是在滨河造成了极大的恐慌,老刑警刘岩,带你破解...
    沈念sama阅读 204,684评论 6 478
  • 序言:滨河连续发生了三起死亡事件,死亡现场离奇诡异,居然都是意外死亡,警方通过查阅死者的电脑和手机,发现死者居然都...
    沈念sama阅读 87,143评论 2 381
  • 文/潘晓璐 我一进店门,熙熙楼的掌柜王于贵愁眉苦脸地迎上来,“玉大人,你说我怎么就摊上这事。” “怎么了?”我有些...
    开封第一讲书人阅读 151,214评论 0 337
  • 文/不坏的土叔 我叫张陵,是天一观的道长。 经常有香客问我,道长,这世上最难降的妖魔是什么? 我笑而不...
    开封第一讲书人阅读 54,788评论 1 277
  • 正文 为了忘掉前任,我火速办了婚礼,结果婚礼上,老公的妹妹穿的比我还像新娘。我一直安慰自己,他们只是感情好,可当我...
    茶点故事阅读 63,796评论 5 368
  • 文/花漫 我一把揭开白布。 她就那样静静地躺着,像睡着了一般。 火红的嫁衣衬着肌肤如雪。 梳的纹丝不乱的头发上,一...
    开封第一讲书人阅读 48,665评论 1 281
  • 那天,我揣着相机与录音,去河边找鬼。 笑死,一个胖子当着我的面吹牛,可吹牛的内容都是我干的。 我是一名探鬼主播,决...
    沈念sama阅读 38,027评论 3 399
  • 文/苍兰香墨 我猛地睁开眼,长吁一口气:“原来是场噩梦啊……” “哼!你这毒妇竟也来了?” 一声冷哼从身侧响起,我...
    开封第一讲书人阅读 36,679评论 0 258
  • 序言:老挝万荣一对情侣失踪,失踪者是张志新(化名)和其女友刘颖,没想到半个月后,有当地人在树林里发现了一具尸体,经...
    沈念sama阅读 41,346评论 1 299
  • 正文 独居荒郊野岭守林人离奇死亡,尸身上长有42处带血的脓包…… 初始之章·张勋 以下内容为张勋视角 年9月15日...
    茶点故事阅读 35,664评论 2 321
  • 正文 我和宋清朗相恋三年,在试婚纱的时候发现自己被绿了。 大学时的朋友给我发了我未婚夫和他白月光在一起吃饭的照片。...
    茶点故事阅读 37,766评论 1 331
  • 序言:一个原本活蹦乱跳的男人离奇死亡,死状恐怖,灵堂内的尸体忽然破棺而出,到底是诈尸还是另有隐情,我是刑警宁泽,带...
    沈念sama阅读 33,412评论 4 321
  • 正文 年R本政府宣布,位于F岛的核电站,受9级特大地震影响,放射性物质发生泄漏。R本人自食恶果不足惜,却给世界环境...
    茶点故事阅读 39,015评论 3 307
  • 文/蒙蒙 一、第九天 我趴在偏房一处隐蔽的房顶上张望。 院中可真热闹,春花似锦、人声如沸。这庄子的主人今日做“春日...
    开封第一讲书人阅读 29,974评论 0 19
  • 文/苍兰香墨 我抬头看了看天上的太阳。三九已至,却和暖如春,着一层夹袄步出监牢的瞬间,已是汗流浃背。 一阵脚步声响...
    开封第一讲书人阅读 31,203评论 1 260
  • 我被黑心中介骗来泰国打工, 没想到刚下飞机就差点儿被人妖公主榨干…… 1. 我叫王不留,地道东北人。 一个月前我还...
    沈念sama阅读 45,073评论 2 350
  • 正文 我出身青楼,却偏偏与公主长得像,于是被迫代替她去往敌国和亲。 传闻我的和亲对象是个残疾皇子,可洞房花烛夜当晚...
    茶点故事阅读 42,501评论 2 343

推荐阅读更多精彩内容